» Overseas Sponsors add colour and a bit of magic as two more schools are opened
  » New Schools herald a new dawn for students of Kalawanchikudy and Thambaddai
  » Overseas sponsors join Rotarians as 2 more schools are ceremonially opened
  » ‘Schools Re-awaken’ project enters its final phase
  » Model Moraketiara School rises from ruins of Mawella Sri Sumangala
  » Rotary Standard Chartered Schools Trust opens Seventh School rebuilt after tsunami
  » Dharmarama Junior School rises again
  » Rotary’s schools rebuilding project hampered by ongoing violence
  » Rotary opens fifth school rebuilt after tsunami in colourful ceremony
  » Rotary opens two more schools amidst festive atmosphere
  » Rotary International Convention showcases Schools Re-awakening project
  » Rotary Sri Lanka Schools Website records One Million hits
  » New Al Aqsa School in Pottuvil is second school to be opened in Schools Re-awaken project
  » Hoops of Steel
  » Rotary Sri Lanka opens first School rebuilt after tsunami amidst festive atmosphere in historic Sri Lankan Village
  » All roads lead to Randombe – the village where it all began!
  » First two schools due to be completed by end November – others close on their heels
  » Rotary continues to lead the way in school rebuilding project
  » “You are the tops!” – a frank assessment from the Head of the Rotary Foundation
  » Schools Re-awakening project forges on despite few hiccups over land
  » Overseas sponsors join Rotarians for groundbreaking ceremony of new school Dharmarama Vidyalaya
  » Colourful ground breaking and foundation stone laying ceremony at Al Aqsa Vidyalaya in Pottuvil
  » Religious rites, festive atmosphere herald first Foundation stone laying
  » Seven Schools set to begin work in next two weeks
  » Room to Read USA to equip libraries in all 25 schools
  » Apex Committee nearing completion of evaluation of all Estimates and
allocation of contracts
  » Every School – a Model School
  » President, Prime Minister of Sri Lanka felicitate Rotary’s Centenary
  » Danish Rotarians conclude successful visit to Sri Lanka
  » Danish Rotarians get first hand experience of Rotary Sri Lanka’s humanitarian efforts
  » Rotary - Standard Chartered Schools Trust
  » Rotary School Aid shifts into top gear
  » Rotary to play key role in the rebuilding of Schools
  » Message from Governor
  » The time is now
     
Kudaththanai Karaiyoor RCTMS, Jaffna
 
Kudaththanai Karaiyoor Roman Catholic Tamil Missionary School is a Primary and Secondary grade school with classes from Grades 1-10(O Level). It is a Type 3 school. The school has a total of 110 students, 54 male and 56 female. It has 12 teachers.
 
Address: Potpathy, Kudathanai, Vadamarachchi, Jaffna
Students: 110
Lead Club: Col North
President:
Shivantha Rodrigo P:
Project Manager: Ms Jeanne Samuel - 0777-880733
Associate Club 1: Jaffna
President:
E. Saravanapavan P:
District Coordinator:
R. Ragunanthanan P: 0777-880733
Director of Schools: Mr. Vinayagaratnam P: 02262220087
Reconstruction Cost: 37million (LKR)
School Sponsors: RIBI
   
Disbursements:
  01. Payment Certificate 1 - LKR 3,183,733.31
02. Payment Certificate 2 - LKR 7,505,352.84
03. Payment Certificate 2 - LKR 2,408,004.51


TOTAL - LKR 13,097,090.66
 
WORK IN PROGRESS AT THE SITE
PROGRESS REPORTS
15th June 2007:
Area is still strictly out of bounds for civilians.Situation being monitored by MoE/project staff.

15th May 2007:
Area is still strictly out of bounds for civilians.Situation being monitored by MoE/project staff.

30 April 2007:
Area is still strictly out of bounds for civilians.Situation being monitored by MoE/project staff.

07 April 2007:
Area is still strictly out of bounds for civilians.Situation being monitored by MoE/project staff.

31 Mar 2007:
Area is still strictly out of bounds for civilians.Situation being monitored by MoE/project staff.

28th Feb 2007:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.

15th Feb 2007:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.

15th Jan 2007:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.

31st Dec 2006:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.

15th Nov 2006:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.

31st Oct 2006:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.

15th Oct 2006:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.

30st Sept 2006:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.

15th Sept 2006:
Area is still out of bounds for civilians.Situation being monitored on a daily basis by project staff.

31st Aug 2006:
Area is still out of bounds for civilians.Situation being monitored on a daily basis by project staff.

15th Aug 2006:
Heavy fighting reported in the area and close to construction site. Hope to get accurate report after site visit when access to area is permitted.

31st July 2006:
Work still remains halted owing to security concerns in the area. Situation being monitored on daily basis.

15th July 2006:
Work still remains halted owing to security concerns in the area. Situation being monitored on daily basis.

30th June 2006:
Work still remains halted owing to security concerns in the area. Situation being monitored on daily basis.

15th June 2006:
Work still remains halted owing to security concerns in the area. Situation being monitored on daily basis.

31st May 2006:
Work remains halted owing to security concerns in the area. Situation being monitored on daily basis.

15th May 2006:
Work continues to be temporarily halted owing to security concerns in the area. Apex Committee continues to monitor security situation on a daily basis with MoE, Contractor and project staff.The security of our workforce remains the highest priority of the Apex Committee.

30th April 2006:
Work temporarily halted owing to security concerns in the area. Apex Committee monitoring situation closely with contractor and project staff.

7th April 2006:
The construction site will be closed for the period 8-20 April for the local New Year holidays. Next update will be as at 30th April 2006.

31st Mar 2006:
Work recommenced after joint inspection on 23rd March. Foundation work -100%, Steel structure -78%.

15th Mar 2006:
Work is temporarily suspended pending report on cement/sand casting blocks. Project Engineer and MoE Engineer will make a joint inspection on quality of work and materials used.

28th Feb 2006:
Project Engineer visited site on 27th feb. Work is progressing satisfactorily. Steel structure erection -25% complete. Foundation work -100% complete. Quality of cent blocks not satisfactory - samples removed for testing.

15th Feb 2006:
Work continues to progress at a satisfactory rate despite the difficult location. Project Engineer will visit site on 27th feb.

31st Jan 2006:
Work is progressing at a satisfactory pace. All foundations are now complete. Other material being prefabricated at another site.

15th Jan 2006:
Construction continues at a reasonable pace. Project Consultant visited the site on 4th January and was pleased with the work completed despite the difficult conditions.

31st Dec 2005:
Reports from site indicate that work is progressing at a reasonable pace with a small workforce. Project Consultant will visit site on 4th Jan 2006 to review the work.

15th Dec 2005:
Construction work commenced on 10th December. Contractor has agreed to increase workforce to make up for late start. Site visit by Engineer due in 1st week of January 2006.

30th Nov 2005:
Construction work still not commenced due to escalation of civil unrest in area. Apex Committee monitoring situation closely.

15th Nov 2005:
Construction work was put off till after the Presidential elections as most of the workforce had to return to their villages to cast their votes.

31st Oct 2005:
Mobilisation of workforce has commenced and materials being stockpiled at site. Expect construction work to begin shortly.

15th Oct 2005:
All paperwork has been finalised and tender awarded. Expect mobilisation of workforce to commence shortly.

30th Sep 2005:
Construction work delayed as drawings had to be also cleared by other political party. Work expected to commence by mid October.

15th Sep 2005:
Work on construction delayed slightly as Contractor had to modify some parts of the design. Expect to commence work by 15th September.

31 August 2005:
Work on construction delayed slightly as Contractor had to modify some parts of the design. Expect to commence work by 15th September.

15 August 2005:
Contractor identified and award of contract expected to be finalised by 20th August. Mobilisation to commence by end August.

31 July 2005:
Award of contract delayed. Expect Foundation laying and construction work to begin by mid August.

15 July 2005:
Await final drawings/estimate from architect/contractor. Expect to award contract in mid July.

30 June 2005:
All paperwork has been completed and award to be made shortly. Expect Foundation laying by 31 July.

21 April 2005:
Preliminary designs and estimates have been forwarded to the Apex Committee for evaluation and award of contract.

7 Feb 2005:
Work has begun to clean out school premises and make preliminary inspections.
Expect to have initial estimates and BOQ’s in hand by last week February.
 
PIX OF DAMAGED SCHOOL AFTER TSUNAMI