 |
| Mathalan RCTMS, Mulaitivu |
| |
| Mathalan Roman Catholic Tamil Missionary School is a Primary grade school with classes from Grades 1-5. It is a Type 3 school. The school has only 63 students, and four teachers |
| |
| Address: |
Mullivaikkal, Mullaitivu,
Mulaitivu |
| Students: |
63 |
| Lead Club: |
Colombo |
| President: |
| Asgi Akbarally |
P: |
 |
|
| Project Manager: |
Mike Masilamani - 0777-880733 |
| Associate Club 1: |
Vavuniya |
| President: |
| Dr K.Thiyagarajah |
P:
|
 |
|
| District Coordinator: |
| R. Ragunanthanan |
P:
0777-880733 |
 |
|
| Director of Schools: |
Mr. Vinayagaratnam P: 0262220087 |
| Reconstruction Cost: |
30.7million (LKR) |
| School Sponsors: |
RC Limasson, Stichting Marthalan Foundation |
| |
|
| Disbursements: |
| |
01. Payment Certificate 1 - LKR 3,410,574.41
02. Payment Certificate 2 - LKR 8,993,087.22
03. Payment Certificate 3 - LKR 5,207,935.95
04. Payment Certificate 4 - LKR 2,500,000.00
TOTAL - LKR 20,111,597.58 |
|
| |
| WORK IN PROGRESS AT THE SITE |
 |
 |
|
| PROGRESS REPORTS |
15th June 2007:
Area is still strictly out of bounds for civilians.Situation being monitored by MoE/project staff.
15th May 2007:
Area is still strictly out of bounds for civilians.Situation being monitored by MoE/project staff.
30 April 2007:
Area is still strictly out of bounds for civilians.Situation being monitored by MoE/project staff.
07 April 2007:
Area is still strictly out of bounds for civilians.Situation being monitored by MoE/project staff.
31 Mar 2007:
Area is still strictly out of bounds for civilians.Situation being monitored by MoE/project staff.
28th Feb 2007:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.
15th Feb 2007:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.
15th Jan 2007:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.
31st Dec 2006:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.
30th Nov 2006:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.
15th Nov 2006:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.
31st Oct 2006:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.
15th Oct 2006:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.
30st Sept 2006:
Area is still strictly out of bounds for civilians.Situation being monitored on a daily basis by project staff.
15th Sept 2006:
Area is still out of bounds for civilians.Situation being monitored on a daily basis by project staff.
31st Aug 2006:
Area is still out of bounds for civilians.Situation being monitored on a daily basis by project staff.
15th Aug 2006:
Work remains halted owing to security concerns in the area. Situation being monitored on daily basis.
31st July 2006:
Work remains halted owing to security concerns in the area. Situation being monitored on daily basis.
15th July 2006:
Work remains halted owing to security concerns in the area. Situation being monitored on daily basis.
30th June 2006:
Work remains halted owing to security concerns in the area. Situation being monitored on daily basis.
15th June 2006:
Work remains halted owing to security concerns in the area. Situation being monitored on daily basis.
31st May 2006:
Work remains halted owing to security concerns in the area. Situation being monitored on daily basis.
15th May 2006:
Work continues to be temporarily halted owing to security concerns in the area. Apex Committee continues to monitor security situation on a daily basis with MoE, Contractor and project staff.The security of our workforce remains the highest priority of the Apex Committee.
30th April 2006:
Work temporarily halted owing to security concerns in the area. Apex Committee monitoring situation closely with contractor and project staff.
7th April 2006:
The construction site will be closed for the period 8-20 April for the local New Year holidays. Next update will be as at 30th April 2006.
31st Mar 2006:
Work progressing well. All bldgs roof cover 100% complete. Block work for walls -100% completed.
15th Mar 2006:
Work continues smoothly and at a good pace. All bldgs roof cover and block work for walls -75% completed.
28th Feb 2006:
Project Engineer visited site on 28th Feb. Work is progressing very well. Steel structure erection complete. Blk work for superstructure done. Roof sheets stockpiled at site.
15th Feb 2006:
Work continues to progress at a satisfactory rate despite the difficult location. Project Engineer will visit site on 27th Feb for inspection.
31st Jan 2006:
Work progressing very well and at a good pace. Steel structure is being erected. Project Consultant vwill visit site again in Mid Feb for inspection.
15th Jan 2006:
Construction continues at a good pace. Project Consultant visited the site on 4th January and was pleased with the work completed despite the difficult conditions.
31st Dec 2005:
Reports from site indicate that work is progressing at a reasonable pace with a small workforce. Project Consultant will visit site on 4th Jan 2006 to review the work.
15th Dec 2005:
Work continues at a reasonable pace. Project Engineer will visit site in first week of January for evaluation of work.
30th Nov 2005:
Construction work continues at reasonable pace. Overall 30% of work complete in all areas.
15th Nov 2005:
Construction work progressing well and on schedule. Foundations complete in all blocks. Few changes included in layout plan.
31st Oct 2005:
Work is progressing well and at a good pace. Foundations in Admin, Music and Classroom blocks almost complete.
15th Oct 2005:
Full workforce mobilised at site and construction work is now in progress.
30th Sep 2005:
Construction work delayed unexpectedly as approval had to be sought from other political party. Intend to commence by mid October.
15th Sep 2005:
Modified design incorporating MoE's recommendations. Work slightly delayed due to this. Expect to lay foundation stone by end Sep.
31 August 2005:
Work on construction delayed slightly as Contractor had to modify some parts of the design. Expect to commence work by 15th September.
15 August 2005:
Paperwork approved and contract awarded. Expect construction work to begin by 25th August.
31 July 2005:
Award of contract delayed. Expect Foundation laying and construction work to begin by mid August.
15 July 2005:
All paperwork has been completed and award to be made shortly. Expect Foundation laying by 31 July.
30 June 2005:
Await final drawings/estimate from architect/contractor. Expect to award contract in mid July.
21 April 2005:
Preliminary designs and estimates have been forwarded to the Apex Committee for evaluation and award of contract.
7 Feb 2005:
Work has begun to clean out school premises and make preliminary inspections.
Expect to have initial estimates and BOQ’s in hand by last week February. |
| |
| PIX OF DAMAGED SCHOOL AFTER TSUNAMI |
 |
 |
|
|
| |