| Address: |
Onthachimadam, Kaluwanchikudy,
Batticaloa |
| Students: |
468 |
| Lead Club: |
Col Regency |
| President: |
| Mario Perumal |
P: |
 |
|
| Project Manager: |
Chamila Wickramasinghe |
| Associate Club 1: |
Mt Lavinia |
| President: |
| Gihan Dalpethado |
P:
|
 |
|
| District Coordinator: |
| Imran Hassen |
P:
0777-377991 |
 |
|
| Director of Schools: |
Mr. Vinayagaratnam P: 0262220087 |
| Reconstruction Cost: |
LKR 57,329,521.00 |
| School Sponsors: |
Rotary Denmark (1), RC Brockton Mass - USA, RC Zagreb - Croatia, RC Wausau - USA, RC Invermere - Canada |
| |
|
| Disbursements: |
| |
01. Payment Certificate 1 - LKR 3,691,336.79
02. Payment Certificate 2 - LKR 3,076,911.10
03. Payment Certificate 3 - LKR 2,727,221.11
04. Payment Certificate 4 - LKR 3,505,591.96
05. Payment Certificate 5 - LKR 3,379,921.53
06. Payment Certificate 6 - LKR 3,846,545.24
07. Payment Certificate 7 - LKR 3,026,902.57
08. Payment Certificate 8 - LKR 1,573,498.99
09. Payment Certificate 9 - LKR 2,183,640.06
10. Payment Certificate 10 - LKR 1,992,316.10
11. Payment Certificate 11 - LKR 5,884,281.57
12. Payment Certificate 12 A - LKR 2,066,349.00
13. Payment Certificate 13,13A,13B - LKR 2,455,710.54
14. Payment Certificate 11 - LKR 4,157,374.00
15. Payment Certificate 11 - LKR 3,596,851.00
16. Payment Certificate 11 - LKR 5,032,929.39
17. Payment Certificate 11 - LKR 1,158,584.00
TOTAL - LKR 53,355,964.95
|
|
| |
| WORK IN PROGRESS AT THE SITE |
 |
 |
|
| PROGRESS REPORTS |
31st August 2007:
New School declared opened on 25th August 2007 in colourful ceremony with overseas sponsors from Rotary Denmark and members of Apex Committee in attendance.
15th August 2007:
New School is now ready for ceremonial opening. Workforce engaged in landscaping and finishing touches before the event which is expected to have overseas sponsors in attendance.
15th July 2007:
"Work is progressing at a feverish pace to complete the construction by mid August 2007.Admin Blk--A – Overall- 70% complete, Admin Blk- -B- Overall- 85%, Single Storied Blk-; . 2-Storied Block – Overall-90%.
"
15th June 2007:
Work continues to progress well. Wiring -60%, Carpentry-20% in all Buildings. Admin Blk--A – roof -20% G.Fl. plaster-100%, Admin Blk- -B- Plaster- G.Fl.-80%, roof -100%, Single Stry Blk- . 2-Stry Blk – Overall-98%.
15th May 2007:
Work is progressing steadily. Wiring, -60%, Capentry-20% in all Buildings. Admin Blk--A – roof -20% G.Fl. plaster-100%, Admin Blk- -B- Plaster- G.Fl.-80%, roof -100%, Single Storied Blk- . 2-Storied Block –Overall-98%.
30 April 2007:
Workforce is now back at full strength following New Year holiday and work pace has picked up appreciably. Contractor does not have any Sinhala labour and so is largely unaffected by the warning about safety of Sinhala labour. Target completion date for school is end June 2007.
07 April 2007:
Site will be closed from 8-23 April for the local New Year holidays. Next Progress report will be on 30th April 2007.
31 Mar 2007:
Work pace has slowed down considerably and contractor has assured Apex Comm that full workforce will be deployed after New year holidays.
28th Feb 2007:
Work continues to progress at a steady pace. Contractor is optimistic of completing school by end June 2007.
15th Feb 2007:
"Work is progressing well and at a satisfactory pace.Admin Block- Wing-A – 1st Fl. Col.s & Bk. Work- 100%
Admin Block- Wing-B –G. Fl. Plaster-70%, F. Fl. Columns, Bk. Work-100%
"
15th Jan 2007:
"The progress of work continues at a satisfactory pace. Admin Block- Wing-A – 1st Fl. Col.s & Bk. Work- 100%. Admin Block- Wing-B –G. Fl. Plaster-70%, F. Fl. Columns, Bk. Work-100%, Single Storeyed Block- 2-Storeyed Block –No progress. Roof Trusses are being fabricated away from site at an alternate location."
31st Dec 2006:
The progress of work on the school has been quite reasonable. The Contractor has faced regular shortages of labour as the demand for both skilled and unskilled labour in the area is now quite high.Overall 60% of the work has now been completed. Both main buildings have now been completed upto Roof Level. Additionally, the internal plastering of the first building is also almost completed.
30th Nov 2006:
"Work is progressing at a disappointingly slow pace.2-Storied Block – 1st Fl. Columns & Bk. Work- 100%, Admin Block- Wing-A – 1st Fl. Columns & Bk. Work- 60%, Admin Block- Wing-B –GF Plaster- 30%, FF Columns, Bk. Work-80%.
"
15th Nov 2006:
Work pace continues to be disappointingly slow owing to drastically reduced workforce. Special Review meeting fixed for 26th November.
31st Oct 2006:
Work is progressing slowly and is behind schedule. 2-stry blk - 1st flr columns & bk wk - 100%. Admin Blk Wing A - Slab - 100%. Admin Blk Wing B - No progress.
30st Sept 2006:
"Work pace has slowed down considerably owing to shortage of labour in the area. 2-Storied Block – 1st Fl. Columns & Bk. Work- 70%, Admin Block- Wing-A – Fl. Slab Shuttering- 85%, Admin Block- Wing-B - G. Fl. Plaster- 30%, F. Fl. Columns, Bk. Work-80%,"
15th Sept 2006:
Work pace has slowed down considerably owing to shortage of labour in the area. 2 stry blk - 1st flr columns & bk wk 70%. No progress in other areas.
31st Aug 2006:
Work progressing at reasonable pace. 2 stry blk - 1st flr columns 100%. Admin Blk Wing A GF bk wk & columns 100%. Admin Blk WingB GF plaster 60%, 1st flr columns, bk wk 80%.
15th Aug 2006:
Work is progressing satisfactorily. 2 stry blk - 1st flr columns 40%. Admin Blk Wing A GF bk wk & columns 80%. Admin Blk WingB slb conc 100% shuttering 100%, GF plaster 30%.
31st July 2006:
Work is progressing satisfactorily. 2 stry blk - 1st flr columns 10%. Admin Blk Wing A GF bk wk & columns 80%. Admin Blk WingB slb conc 60% shuttering 100%, RF 80%.
30th June 2006:
Work now progressing at a fair pace. Admin Blk wingA - G F Bk wk & columns 80%, Admin Blk wing B - Slab concreting 60%.2 stry Blk Flr slab shuttering 80% RF 20%.
15th June 2006:
Work has now recommenced with increased workforce after resolution of earlier issue. Expect optimum workforce to be in operation by end of the month.
31st May 2006:
Pace of work has slowed down considerably as Contractor under pressure from external forces regarding the non-payment of 'taxes'.
15th May 2006:
Work has resumed after new year holidays and is at a fair pace. G Flr Columns & Brk wk-80% in Wing A of 2 storeyed blk. Column Foundations 70% in Wing B. Admin Blk - columns & Brk wk - 100%. Single storeyed bldg - columns & bk wk - 100%.
30th April 2006:
Work has resumed after new year holidays and is at a fair pace. G Flr Columns & Brk wk-80% in Wing A of 2 storeyed blk. Column Foundations 70% in Wing B. Admin Blk - columns & Brk wk - 100%. Single storeyed bldg - columns & bk wk - 100%.
7th April 2006:
The construction site will be closed for the period 8-20 April for the local New Year holidays. Next update will be as at 30th April 2006.
31st Mar 2006:
Work is going on at a fair pace. G Flr Columns & Brk wk-50% in Wing A of 2 storeyed blk. Column Foundations 50% in Wing B. Admin Blk - columns & Brk wk - 40%
15th Mar 2006:
Work is progressing at a fair pace. Admin Blk column foundations almost complete.
28th Feb 2006:
Work is progressing at a satisfactory pace. Work on Foundations of main blks in progress.
15th Feb 2006:
Construction work is now in progress in cleared area.
31st Jan 2006:
Temporary shelters have now been relocated and construction work has just started.
15th Jan 2006:
Workforce is now mobilised at site and clearing of site is in progress. However Contractor is unable to commence construction work because some of the temporary shelters set up by MoE are on the site and need to be relocated to ensure safety of students.
31st Dec 2005:
Contractor had a change of heart and resubmitted fresh quote at very competitive rate and was awarded tender.
15th Dec 2005:
Apex Committee have decided to call for fresh tenders after contractor refused to reduce his rates.
30th Nov 2005:
Foundation stone laid pending final negotiations with contractor whose prices still comparatively high. Apex Committee has requested him to revise his estimate downwards or lose tender.
15th Nov 2005:
Issue of LoA delayed slightly due to ongoing negotiations with contractor. Expect award to be issued and construction to commence by end November.
31st Oct 2005:
Paperwork is still not completed. Still await structural drawings and amendments to BOQ before finalising award.
15th Oct 2005:
Finalisation of tender delayed unexpectedly. Intend to finalise by mid October and lay foundation stone.
30th Sep 2005:
Finalisation of tender delayed unexpectedly. Intend to finalise by mid October and lay foundation stone.
15th Sep 2005:
In the process of finalising tender. Construction work to commence before end September.
31 August 2005:
Construction work delayed slightly - will now commence by mid September.
15 August 2005:
Paperwork approved and contract awarded. Expect construction work to begin by 25th August.
31 July 2005:
Award of contract delayed. Expect Foundation laying and construction work to begin by mid August.
15 July 2005:
All paperwork has been completed and award to be made shortly. Expect Foundation laying by 31 July.
30 June 2005:
Await final drawings/estimate from architect/contractor. Expect to award contract in mid July.
21 April 2005:
Preliminary designs and estimates have been forwarded to the Apex Committee for evaluation and award of contract.
7 Feb 2005:
Work has begun to clean out school premises and make preliminary inspections.
Expect to have initial estimates and BOQ’s in hand by last week February. |
| |
| PIX OF DAMAGED SCHOOL AFTER TSUNAMI |
 |
 |
 |
|
|