| Dharmarama K. Vidyalaya, Galle |
| |
| Dharmarama Vidyalaya is a Primary and Secondary grade school with classes from Grades 1-10(O Level). It is a Type 3 school. The school has 28 teachers and 781 students 439 male and 342 female. |
| |
| Address: |
Ahangama, Galle,
Galle |
| Students: |
781 |
| Lead Club: |
Col Mid City |
| President: |
| S. P. Nadarajah |
P: |
 |
|
| Project Manager: |
DGN Bobby Senaweera - 0777-533066 |
| Associate Club 1: |
Galle |
| President: |
| Herbert Paulas |
P:
|
 |
|
| District Coordinator: |
| Imthiaz Ismail |
P:
0777-576527 |
 |
|
| Director of Schools: |
P. Karunadasa P: 0777-301996 |
| Reconstruction Cost: |
47.22million (LKR) |
| School Sponsors: |
USA - American Jewish Joint Distribution Committee, Twin School : Hall School of London. UK |
| |
|
| Disbursements: |
| |
01. Mobilization Advance Paid - LKR 9500000
02. Payment Certificate 1 - LKR 6,146,453.96
03. Payment Certificate 2 - LKR 7,536,319.32
04. Payment Certificate 3 - LKR 5,803,379.71
05. Payment Certificate 4 - LKR 3,886,808.57
06. Payment Certificate 5 - LKR 3,694,408.10
07. Payment Certificate 6 - LKR 3,586,858.57
08. Payment Certificate 7 - LKR 7,525,736.87
09. Payment Certificate 8 - LKR 3,000,000.00
10. Recovery of Advance - LKR -5,519,300.25
11. Certificate 9 - LKR - 3,313,428.75
TOTAL - LKR 53,998,393.85
|
|
| |
| WORK IN PROGRESS AT THE SITE |
 |
 |
|
| PROGRESS REPORTS |
15th Nov 2006:
New School ceremonially opened in a colourful ceremony on Sunday 5th November in the presence of a large and distinguished gathering. 781 lucky boys and girsl will now continue their education in their new school with all the modern facilities to assist them.
31st Oct 2006:
Final finishing touches being done on the landscaping and planting of lawns. The opening ceremony on Sunday 5th November is eagerly awaited by the whole village.
15th Oct 2006:
Opening ceremony fixed for Sunday 5th November 2006.
30st Sept 2006:
Still await sponsor's confirmation of new date in October for opening ceremony.
15th Sept 2006:
Sponsors unavailable during month of September 2006. Await new date in October for opening ceremony.
31st Aug 2006:
All construction work is now complete and school is ready for occupation. Await Sponsors confirmation of new opening date.
15th Aug 2006:
Opening ceremony postponed indefinitely on request by PTA. Closure of all schools in the country for two weeks owing to security concerns, has caused anxiety amongst parents & teachers.
31st July 2006:
School construction 95% complete. Assembly Hall roof - 50% complete. Opening ceremony fixed ofr 20th August 2006.
30th June 2006:
Work continues at good pace. U Blk, Admin Blk ,T Blk, Perimeter drain and Chain link fence - 100% complete. Assembly Hall - walls 100%. Work now on to move O/H Power lines. Water tank columns sump walls-100%. Target completion date end July.
15th June 2006:
Work continues at satisfactory pace. U Blk, Admin Blk ,T Blk all complete. Perimeter drain and Chain link fence - 100%, Assembly Hall - walls 100%. Water tank columns 100%. Target completion date end July.
31st May 2006:
Work progressing well and on schedule. U Blk - complete, Admin Blk - complete.T Blk - 95% complete. Chain link fence - 100%, Assembly Hall - walls 50%. Target completion date mid July.
15th May 2006:
Work continues to progress well and at a fair pace. U Blk - overall 95% complete, Admin Blk Overall 85% complete.T Blk - 90% complete. Chin link fence - 90%, Assembly Hall - walls 25%.
31st Mar 2006:
Work progressing well. U Blk - Painting 80%, T Blk - Plaster 80%, Admin Blk - Wall plaster -100%. Perimeter drain - 80%. Chin link fence - 50%, Assembly Hall - excavations - 60%.
7th April 2006:
The construction site will be closed for the period 8-20 April for the local New Year holidays. Next update will be as at 30th April 2006.
31st Mar 2006:
Work continues to progress well. U Blk - Painting 50%, T Blk - Plaster 50%, Admin Blk - Wall plaster -75%.Boundary wall complete. Perimeter drain - 70%.
15th Mar 2006:
Work pace and quality remain steady. U Blk - Wall plaster - 100%, T Blk - Roof tiling -100%, Admin Blk - Wall plaster -50%.
28th Feb 2006:
Work continues to progress well and is of high quality. U Blk - Roof work - 100%, T Blk - Roof trusses -100%, Admin Blk - Roof trusses -100%, Bkwk-100%
15th Feb 2006:
Work is progressing very well and is of high quality. U Blk - roof work - 60%, T Blk - Roof trusses -100%, Admin Blk - tie beams in progress, Perimeter drain - 80%
31st Jan 2006:
Work is progressing very well and is of high quality. U Blk - roof trusses - 100%, T Blk - Bk work -100%, Admin Blk - tie beams in progress, Boundary wall - 100%.
15th Jan 2006:
Work continues to progress very well and on schedule. Overall 50% of work completed. Target date for completion 30th April 2006.
31st Dec 2005:
Work continues to progress very well and on schedule. Overall 50% of work completed. Target date for completion 30th April 2006.
15th Dec 2005:
Work continues to progress very well and on schedule. U Block brickwork 100% complete. T Block 75%. Roof trusses for both U & T blocks 100% complete.
30th Nov 2005:
Work is progressing well and at a good pace. All foundations complete.
15th Nov 2005:
Work is progressing well and at a good pace. All foundations complete.
31st Oct 2005:
Work continues at a steady pace and is slightly ahead of schedule. Foundations complete in Admin and two other blocks.
15th Oct 2005:
Work is now progressing well and is on schedule.
30th Sep 2005:
Work is now in progress and at a steady pace. Total workforce now mobilised and material stockpiled at site.
15th Sep 2005:
Construction work was slightly delayed and began only on 13th. Work is now in progress.
31 August 2005:
Foundation stones were laid on 26th August. Construction expected to commence from 1st September.
15 August 2005:
Slight delay in paperwork to accommodate an assembly hall for the school. Foundation stone laying ceremony has been fixed for 26th August.
31 July 2005:
Filling of land and soil testing completed. Foundation laying and Construction work to begin by mid August.
15 July 2005:
Filling of land is almost complete but soil testing has to be done. Construction work may begin only by mid August.
30 June 2005:
Filling of land is in progress. Expect to commence construction work by end July.
21 April 2005:
Preliminary designs and estimates have been forwarded to the Apex Committee for evaluation and award of contract.
7 Feb 2005:
Work has begun to clean out school premises and make preliminary inspections.
Expect to have initial estimates and BOQ’s in hand by last week February. |
| |
| PIX OF DAMAGED SCHOOL AFTER TSUNAMI |
 |
 |
|
|
| |